jack
post May 15 2008, 12:10 PM
Post #1



*

Group: Members
Posts: 1
Joined: 15-May 08
Member No.: 4,563



Hello all,

I would like an opinion on whether a DG set can be avoided in our 1 MW incinerator power plant. The overhead load comes to 200KW. We have 2 generator of 560KW capacity running on producer gas. startup takes about 1/2 hour. Utility power is available & power plant is only operational for 8 hrs/day. Is it possible to float the generators on utilility power during start up & gradually be loaded as the plant comes to full gas production.
Any comment would be greatly appreciated.
Go to the top of the page
 
+Quote Post

Reply to this topicStart new topic
1 User(s) are reading this topic (1 Guests and 0 Anonymous Users)
0 Members:

 



Collapse

> Similar Topics

    Topic Title Replies Topic Starter Views Last Action
No New Posts   1 dip04051978 1,134 16th August 2003 - 10:08 PM
Last post by: marke
No New Posts   2 bobo73 1,068 23rd May 2005 - 07:35 PM
Last post by: marke
No New Posts   2 rajnikantsangani 490 19th June 2005 - 06:45 PM
Last post by: marke
No New Posts   6 bss_ganesh 1,913 21st August 2005 - 05:08 AM
Last post by: -Anonymous-
No New Posts   1 bob 538 22nd November 2005 - 07:27 AM
Last post by: marke



RSS Lo-Fi Version Time is now: 1st December 2008 - 09:07 PM
hosted by : L M Photonics Ltd