Dear members
We have a generator and stepup transformer with Yd11 vector group which is to be synchronised with the grid. We also have a unit transformer fed by the same generator (Dy11) which has to be paralleled with a station transformer( YY) which has input from the grid. pl let me know whether synchronisation and paralleling with the above vector groups is possible |
|
|
|
![]() ![]() |